Welcome to the Port of Palm
Beach
Navigation Feasibility Study
Updated March 2008
Click Here For a Printable Version
The Port of Palm Beach is the Local Sponsor for a federal
study to assess the need for channel expansion. The study,
called the Palm Beach Harbor Navigation Feasibility Study,
is being conducted by the United States Army Corps of
Engineers (USACE), Jacksonville District. The study was
initiated in late 2005, but was unable to proceed due to a
lack of federal funds. New cost sharing agreements between
the Port and USACE are now allowing the study to commence.
About the Study
The Palm Beach Harbor Navigation Feasibility Study will
assess the costs and benefits associated with improvements
to the federally-designated deep water channel and turning
basins serving the Port of Palm Beach. The success of the
Port is dependent upon deep water access through the
federal channel. The current channel depths were
established approximately 40 years ago and the Port is
increasingly losing business opportunities as a result of
channel limitations. The study will analyze alternatives
to improve access for the existing fleet and also to allow
for increased vessel length and draft, while avoiding or
minimizing impacts to environmental resources.
The Feasibility Study is expected to take three years to
complete and is a cost shared by the Federal Government
and the Port of Palm Beach (known as the non-Federal
sponsor). The study will include in-depth analysis of
engineering, environmental and economic issues associated
with channel widening and deepening to improve vessel
access and navigational safety, and will also include
extensive public and agency coordination at the local,
state and federal levels. A complete Environmental Impact
Statement (EIS) will be prepared as part of the
Feasibility Study.
The culmination of the planning process is the selection
of the recommended plan or the decision to take no
action. The alternative plan that reasonably maximizes net
economic benefits consistent with protecting the Nation's
environment, the National Economic Development (NED) plan,
shall be selected. The NED plan will be recommended for
consideration by Congress as authorized modifications to
the federal harbor project.
Background
An Expedited Reconnaissance Report conducted in 2001 by
the United States Army Corps of Engineers (USACE)
concluded that, based on preliminary findings, there was a
federal interest in pursuing harbor improvements. In
August of 2005, the Port of Palm Beach District and USACE
executed an agreement to partner in the Feasibility Study
to further define the federal interest in harbor
expansion. The study was stalled when a federal
appropriation bill was not passed by Congress in 2006;
however, a modification to the agreement is now allowing
the study to begin using the Port’s funding share.
Public Input
The Feasibility Study will encourage public input at
several key stages in the study process. The first major
public meeting, the National Environmental Policy Act (NEPA)
Scoping Meeting, was held on
January
9th, 2008, 3:00 p.m. at the Port of Palm Beach.
The scoping meeting is held at the beginning of the study
process to provide the public information about the study
and to solicit input on issues and concerns regarding the
study scope. A summary of the meeting and related
materials are available on the United States Army Corps of
Engineers website at:
http://planning.saj.usace.army.mil/envdocs/envdocsb.htm#Palm-Beach.
Channel Improvement Alternatives
The graphic entitled “Study Areas for Potential
Improvements,” is provided at the link below. This graphic
shows the conceptual channel improvement alternatives for
the study, based on input from the Port, Palm Beach Harbor
Pilots, and existing port users. The Feasibility Study
process requires that all alternatives be considered and
evaluated. During the Feasibility Study analysis, a given
alternative may be eliminated or modified because of
impacted environmental resources, insufficient national
economic benefits, engineering practicability and/or lack
of real navigation improvement or safety. Additional
improvement alternatives may also be added to the study as
a result of user and public input.

For a
PRINTABLE version of the above image, click here.
Schedule
A tentative schedule of milestone dates has been developed
and is provided below. The schedule is a working document
and will be updated throughout the project with special
attention towards creating opportunities for public input.
|
Palm Beach Harbor Navigation
Feasibility Study
Milestone Schedule
Draft Dated October 31, 2007 |
|
Activity/Meeting |
Date |
Status |
|
USACE
Kick-Off Meeting |
October 19, 2007 |
Complete |
|
Economic Data Collection |
Initiated October 2007
|
Ongoing through 2008 |
|
NEPA
Scoping Meeting
(1) |
January 9, 2008, 3pm,
Port of Palm Beach |
Complete |
|
Environmental Field Data Collection |
January 2008 |
Expected to occur
through September 2008 |
|
Feasibility Scoping
Meeting
(2) |
Spring 2008 |
Exact date to be
determined |
|
Release
Draft Report (Combined Feasibility Study and
Environmental Impact Statement) for public review &
comment |
February 2010 |
Exact date to be
determined |
|
Public
Meeting on Draft Report |
March 2010 |
Exact date to be
determined |
|
Notes:
(1) Held at the beginning of the study
process to solicit public concerns and issues
regarding the study scope
(2) Held after the initial environmental inventory
and economic analyses are complete to identify
problems and opportunities. |
For
More Information
For
questions, concerns or additional information, please
contact
Mr. Rick McMillen direct
by clicking on his name for his email address.
For a printable version
of this study,
please click here.
Requires Adobe Reader.
For a
printable version of the graphic only,
please click here. Requires Adobe Reader.
Disclosure Statement
The material presented
in this site is believed to be accurate at the time of its
posting, but much of the information here is continually
changing and the accuracy of this material cannot be
guaranteed. All official documents of the Port of Palm
Beach fall under the various public information laws, and
the official versions may be obtained through the Office
of Administration. Material on this site may be
reproduced with attribution, but we recommend you verify
the accuracy with the Office of Administration prior to
reproduction.
All communications with
the Port of Palm Beach and its employees become a matter
of public record and are subject to the various State and
Federal regulations concerning public records. E-mail
directed to the Port of Palm Beach or its employees may be
retained as part of the public record, and these
communications may be available through public information
requests. Because of the public information nature of
this website, users should have no assumption of privacy
of any kind, as any information you or your system may
provide can become public information.
All graphics, logos,
artwork, layout and text contained on this site are
Copyright (list years) by the Port of Palm Beach District,
Florida. Materials may be used with attribution with the
exception of Port logos, seals and emblems. Permission to
use these materials may be granted by request to the
Executive Director.
The Port of Palm Beach
in no way endorses any specific company or product
mentioned on this site or any other website affiliated
with the Port of Palm Beach District. |